The Spoilbank Marina will be delivered in two key stages. To increase opportunities for local businesses to work on the project, these stages have been broken down into work packages.
Stage 1
Stage 2
Package 2
(2a) Excavation of the marina basin and reclamation of some onshore areas.
(2b) Dredging of the new navigation channel.
(2c) Sourcing of rock and construction of breakwaters and revetments.
Package 3
Construction of marine structures (boat ramp, marina pens, public jetty, navigation aids)
Package 4
Landside civil works (carpark, internal roads and landscaping)