The old Tower, which could no longer meet the needs of the port’s growing operations, was brought down in a controlled environment on Saturday, 28 September 2019.
The Tower, which was built in 1968, was becoming increasingly confined for operational staff and was unable to be upgraded with modern equipment. The building had become maintenance-intensive and in future years, would not be safe to maintain.
Pilbara Ports Authority’s Engineering & Infrastructure and Marine Operations teams worked closely with contractors McMahon Services and WGA Engineering to ensure the felling of the Tower occurred smoothly and most importantly, safely.
Pilbara Ports Authority is pleased to report that no harm or injury was sustained by its staff or contractors before, during or after the felling.
Shipping operations are now controlled in the new high-technology Hedland Tower – Integrated Marine Operations Centre, which was officially opened on 30 July 2019.
The Hedland Tower houses state-of-the-art vessel traffic control systems, equipment and emergency response facilities that will steer the safe and efficient movement of vessels through the harbour for the next 50 years.
A commemorative book of the Tower is being produced to capture the Tower’s history.
The Tower’s lift car and other miscellaneous items have been gifted to the Port Hedland Historical Society, with plaques and the iconic blue doors to be displayed in the Hedland Tower reception area.